Problem Summary
Update Material Group 5 and Profit Centers (if Material exists in Plant) in the material Master as a part of Reorg.
Admin Info
Purpose
|
2014 Bus Reorg Systems Realignment update material group5
|
Requested by
|
Rahul Attarde, Babu Vanamali
|
Issue Date
|
09-18-2014
|
Resolved by
|
Adithya, Prudvi
|
Resolved Date
|
09-18-2014
|
Document Status
|
Completed
|
Detailed Problem Description
(Include Screen Shots if required )
Update Material Group 5 and Profit Center in the Material Master as a part of REORG Project.
Solution Analysis and Recommendations
(Include Screen Shots if required)
When the material is existing in plants we can use the program which calls the LSMW and updates the profit center and material group 5 in the material masters.
When the material does not exist in the plants we can use the LSMWs to update only material Group 5 field in the material master.
Resolution
Run the background Program and LSMWs
1. ZMVGR5
2. ZREORG
MATERIAL
Currently we are updating Material Group 5 for those materials which are extended to the Sales Organizations 1400, 1700, 400.